Exhibit 2.1—Key milestones were not met—text version
2014 Spring Report of the Auditor General of Canada
Exhibit 2.1—Key milestones were not met
This timeline shows the initial and actual key milestone dates for the request for information (RFI) and the request for proposals (RFP).
Activity | Initial timeline | Actual timeline |
---|---|---|
Release of the RFI | March 2008 | 7 August 2008 |
Industry response to RFI | April 2008 | 22 September 2008 |
Release of the RFP | September 2008 | 29 April 2009 |
RFP closes | November 2008 | 22 June 2009 |
Evaluation completed | January 2009 | 13 July 2009 |
Contract awarded | June 2009 | 14 August 2009 |
Service commences under the new contract | 1 December 2009 (six-month transition period from contract award) |
1 December 2009 (three-month transition period from contract award) |
Source: Adapted from Public Works and Government Services Canada documents. |